RIEL Real Estate Corporation reports that the construction of Forward RC is underway. According to the project manager, in section A, the entrance group finishing is performed, the installation of elevator portals has been completed, the installation and start-up work of elevators continues, and metres for cold and hot water supply and heat supply metres have been installed. The finishing of the staircases is underway.

In section B, metres for metering devices for cold and hot water and heat supply have been installed, and the entrance group is being finished. The section lighting is ready.

Smoke exhaust, ventilation and fire extinguishing systems in the parking lot are ready. Screed pouring is performed, and preparations for gate installing continue.

Neighbourhood improvement is being completed.

You can always find out about the purchase of parking in Forward RC and the complex construction progress in our company sales department. Contacts are available at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

ООО «РЫБАЛКО-КОМПАНИ»

ООО «ФОРВАРД ДЕВЕЛОП»

ООО «ЭЛИЗИУМ БУД»

Join our social networks
Contact us in convenient way
(044) 499-98-86
Feedback
The exchange rate as of 11/21/2024 is 41.35 UAH.
Sales departments
Kyiv, str. Konovaltsya, 30
Kyiv, 56, Ukrainian Air Force avenue
© 2024  Forward. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.