In section V, the vertical of the fourth floor is arranged

October 04, 2021

RIEL Real Estate Corporation reports that the construction of Forward RC is underway. According to the project manager, in section V the vertical of the fourth floor is arranged.

Meanwhile, in section A, the builders have completed the laying of external and internal walls, the window structures are installed from the 2nd to the 11th floors.

It is also reported that the construction of the roof is about to begin – the laying of a vapor barrier, insulation and installation of a waterproofing membrane, insulation of the facade are being performed.

Parking is 90% ready.

You can always find out about the purchase of apartments in the Forward RC and information on the progress of the construction of the complex from the company's sales departments. Contacts are available at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

ООО «РЫБАЛКО-КОМПАНИ»

ООО «ФОРВАРД ДЕВЕЛОП»

ООО «ЭЛИЗИУМ БУД»

Join our social networks
Contact us in convenient way
(044) 499-98-86
Feedback
The exchange rate as of 4/30/2024 is 39.69 UAH.
Sales departments
Kyiv, 56, Ukrainian Air Force avenue
© 2024  Forward. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.