Roofing works have almost been completed in section B
RIEL Real Estate Corporation reports that the construction of Forward RC is underway. According to the project manager, the roofing works in section B have almost been completed (95% ready); floor tiles from the 4th to the 11th floors have been laid, now they are laid on the 2nd and 3rd floors; heating radiators have been mounted and connected.
In section A, fixtures are being installed, heating radiators are being connected and appliances are being arranged, cold and hot water and electricity consumption meters.
In the parking lot, the laying of engineering networks is in progress: smoke exhaust, ventilation, water extinguishing systems. Arrangement of an individual heat point and fire-pumping equipment is being carried out.
The site improvement work is underway – asphalt pavement is laid, a retaining wall is equipped.