To the news list

Floor tiles are being laid in section B

June 14, 2023

RIEL Real Estate Corporation reports that the construction of Forward RC is in progress. According to the project manager, floor tiles are being laid in Section B and roof work is almost over. The builders completed the decoration of the walls and ceiling in the common facilities and on the flights of stairs, and installed apartment doors. At the same time, heating radiators are being installed.

In Section A, floor tiles have been laid, heating radiators and electrical panels have been installed, and lighting fixtures are being installed.

The laying of engineering networks in the parking lot is underway. The doors in the cells are equipped, preparations are being made for screed pouring.

You can always find out about the purchase of apartments in Forward RC and the complex construction progress in the company sales department. Contacts are available at the link.

We will call you back, advise, select the best options
Phone number *
Thank you for your application! We will contact you shortly.
Subscribe to news and promotions
Thank you for subscribing to our newsletter!
Constructors

ООО «РЫБАЛКО-КОМПАНИ»

ООО «ФОРВАРД ДЕВЕЛОП»

ООО «ЭЛИЗИУМ БУД»

Join our social networks
Contact us in convenient way
(044) 499-98-86
Feedback
The exchange rate as of 5/9/2024 is 39.51 UAH.
Sales departments
Kyiv, 56, Ukrainian Air Force avenue
© 2024  Forward. All rights reserved.Privacy policy
Made in WEZOM
This site uses cookies for more comfortable work of the user. By continuing to browse the site, you agree to the use of cookies.